Due diligence on Bangladesh Southwest Transmission Grid Expansion Project was successfully completed by RMA in April 2018. The project consists of construction of Gopalganj (North) 400/132 kV substation, Barisal (North)-Gopalganj (North)-Faridpur 230 kV double circuit transmission line, Bogra (West)-Rohanpur 400 kV double circuit transmission line, 400/230 kV Bogra (West) GIS substation, 400/132 kV Rohanpur GIS substation, Chapainawabganj-Rohanpur 132 kV double circuit transmission line and a set of line-in line-out connection. The total loan of $ 350 million will be provided by the Asian Development Bank.
- Client:
- Asian Development Bank (ADB)
- Date:
- 2016-2017
- Category:
- Due Diligence on Energy Sector Projects