RMA’s senior consultants worked as a part of the international team to assist the Tanzania Ministry of Energy and Minerals (MEM) and the Energy and Water Utilities Regulatory Commission (EWURA) to develop and establish the pricing policy for grid connected and mini-grid based small power plants that use renewable energy, and to develop the technical guidelines for grid connection of embedded generators. Conducted several seminars and workshops in Tanzania for developers, utility engineers, ministry officials and regulatory staff, to discuss optional tariff setting mechanisms, and to present the proposed tariffs and technical guidelines. The policies, pricing methodology and technical guidelines developed by the RMA consultants have since been implemented in Tanzania.

Client:
The World Bank/Ministry of Energy and Minerals
Date:
2007-2009
Category:
Electricity Utility Planning, National Energy Policy & Planning, Renewable Energy Development